New TopShim run:

version = topshim 2.4.0
date = 2024-10-10
time = 19:52:01.921
command = topshim  convcomp tuneaxyz

FINE SHIMMING

Parameters:

probe = Z116098_0395
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 13C
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
Iteration  1: FWHM Before= 4.6 Hz, Target= 0.4 Hz, After= 1.0 Hz
Iteration  2: FWHM Before= 1.0 Hz, Target= 0.4 Hz, After= 1.4 Hz
Iteration  3: FWHM Before= 1.4 Hz, Target= 0.2 Hz, After= 1.1 Hz
Iteration  4: FWHM Before= 1.1 Hz, Target= 0.4 Hz, After= 0.3 Hz
Shim succeeded

Lineshape quality factor (1D spectrum, spinning) = 1.14


Performing tune after shimming
tune lock level increase = 1.1

shim changes: 
Z	-37
Z2	-54
Z3	+164
Z4	-352
Z5	+109
X	+137
Y	+96

duration = 3 min 14 sec
completed successfully
finished Thu Oct 10 19:55:14 2024


========================================================================